Mostrar el registro sencillo del ítem

dc.contributor.advisorGálvez Paredes, José Alcides
dc.contributor.authorGarcia Chavarria, Howard Alan
dc.creatorGarcia Chavarria, Howard Alan
dc.date.accessioned2022-03-13T01:10:58Z
dc.date.available2022-03-13T01:10:58Z
dc.date.issued2022
dc.identifier.urihttps://hdl.handle.net/20.500.12759/8742
dc.description.abstractLa presente tesis titulada: “Implementación de Last Planner System en la planificación y control de obra de la I.E. N° 81509, CP Chiclin, Chicama, Ascope, La Libertad”, tuvo como objetivo determinar si la aplicación de la metodología del sistema Last Planner mejorara la planificación y control de obra en la ejecución del proyecto: Rehabilitación del Local Escolar N° 81509 Rafael Larco Herrera, CP Chiclin, Chicama, Ascope, La Libertad. La metodología de investigación que fue aplicada fue la de un Diseño Pre Experimental Longitudinal, ya que la información fue recogida directamente de la obra, para seguidamente ser analizada mediante la aplicación de la metodología Last Planner System y evaluar los efectos que su aplicación produce en el proyecto. La población y muestra del estudio está enmarcada en las partidas que más incidencia representaron en la obra. Por otro lado, la implementación del LPS empezó con la Planificación Maestra donde se contó con la participación de los involucrados en el proyecto, donde se asumieron compromisos para el cumplimiento de los objetivos trazados y mejorar la planificación y control de las actividades programadas. Asimismo, se llevó a cabo la sectorización de las actividades con el fin de establecer los trenes de trabajo, en el cual se verifico los metrados y se buscó que los sectores estén balanceados tanto en capacidad y demanda para que las cuadrillas puedan producir los mismo cada día, generando de esta manera menores errores y logrando mejorar la curva de aprendizaje. También se llevó a cabo la Planificación Lookahead el cual conto con un horizonte de 4 (cuatro) semanas, junto a una planificación semanal donde se realizó el análisis de las restricciones de las tareas programadas en la semana siguiente. De igual forma, se analizó el Porcentaje de Plan Cumplimiento (PPC), el cual es un indicador de la confiabilidad de las actividades que habían sido programadas, donde se buscó superar un PPC meta de 75% para el proyecto. Al mismo tiempo se evaluaron las Causas de No Cumplimiento (CNC), donde se identificaron las causas, y así tomar las acciones correctivas necesarias para mejorar el cumplimiento de las actividades. Finalmente, se analizó los resultados obtenidos para establecer conclusiones, y de esta manera generar un aporte positivo en la planificación y control de las obras publicas y privadas en el país.es_PE
dc.description.abstractThe present thesis entitled: “Implementation of the Last Planner System in the planning and control of the work of the I.E. N° 81509, CP Chiclin, Chicama, Ascope, La Libertad”, had as objective to determine if the application of the methodology of the Last Planner system would improve the planning and control of work in the execution of the project: Rehabilitation of the School Premises N° 81509 Rafael Larco Herrera, CP Chiclin, Chicama, Ascope, La Libertad. The research methodology that was applied was that of a Longitudinal Pre Experimental Design, since the information was collected directly from the work, to then be analyzed by applying the Last Planner System methodology and evaluating the effects that its application produces in the draft. The population and sample of the study is framed in the games that represented the most incidence in the work. On the other hand, the implementation of the LPS began with the Master Planning, which involved the participation of those involved in the project, where commitments were made to fulfill the established objectives and improve the planning and control of the programmed activities. Likewise, the sectorization of the activities was carried out in order to establish the work trains, in which the metering was verified and it was sought that the sectors are balanced both in capacity and demand so that the crews can produce the same each day, thus generating fewer errors and improving the learning curve. Lookahead Planning was also carried out, which had a horizon of 4 (four) weeks, together with a weekly planning where the analysis of the restrictions of the tasks scheduled in the following week was carried out. Similarly, the Compliance Plan Percentage (PPC) was analyzed, which is an indicator of the reliability of the activities that had been programmed, where it was sought to exceed a target PPC of 75% for the project. At the same time, the Causes of Non-compliance (CNC) were evaluated, where the causes were identified, and thus take the necessary corrective actions to improve compliance with the activities. Finally, the results obtained were analyzed to establish conclusions, and in this way generate a positive contribution in the planning and control of public and private works in the country.en_US
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada Antenor Orregoes_PE
dc.relation.ispartofseriesT_CIVIL_2048
dc.rightsinfo:eu-repo/semantics/closedAccesses_PE
dc.rights.urihttps://creativecommons.org/licenses/by/4.0/es_PE
dc.sourceUniversidad Privada Antenor Orregoes_PE
dc.sourceRepositorio institucional - UPAOes_PE
dc.subjectPlanificaciónes_PE
dc.subjectLast Planner Systemes_PE
dc.titleImplementación de Last Planner System en la planificación y control de obra de la I.E N° 81509 CP Chiclin, Chicama, Ascope, La Libertades_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada Antenor Orrego. Facultad de Ingenieríaes_PE
thesis.degree.nameIngeniero Civiles_PE
thesis.degree.disciplineIngeniería Civiles_PE
dc.subject.ocdehttp://purl.org/pe-repo/ocde/ford#2.01.00es_PE
renati.advisor.orcidhttps://orcid.org/0000-0002-2100-4241es_PE
renati.author.dni47092473
renati.advisor.dni18217072
renati.typehttp://purl.org/pe-repo/renati/type#tesises_PE
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.discipline732016es_PE
renati.jurorVertiz Malabrigo, Manuel Alberto
renati.jurorRodriguez Ramos, Mamerto
renati.jurorDurand Orellana, Rocio del Pilar
dc.publisher.countryPEes_PE


Ficheros en el ítem

Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(es)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/closedAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/closedAccess