dc.description.abstract | El presente estudio de investigación responde al siguiente problema de investigación:
¿Cuál es la implementación del Last Planner System para mejorar el cumplimiento de
plazos de ejecución del proyecto hospital de Ayabaca, Piura - 2022? Y tiene como
objetivo general realizar la implementación del Last Planner System para mejorar el
cumplimiento de plazos de ejecución del proyecto hospital de Ayabaca, Piura – 2022.
y la hipótesis general que se verificó fue: La implementación del Last Planner System
mejora significativamente el cumplimiento de plazos de ejecución del proyecto Hospital
de Ayabaca, Piura - 2022. El método de investigación es el cuantitativo y longitudinal;
tipo de investigación aplicada; con un nivel de investigación descriptivo explicativo y
de diseño no experimental con carácter transversal. La muestra está conformada por
la caracterización del proyecto Hospital de Ayabaca – Piura. Para ello se utilizaron
técnicas de recolección de datos como observación y análisis documental que
ayudaron a tabular la información en el software Microsoft Excel donde se obtuvo
información porcentual y que se graficaron en diagramas y tablas. El plan de
investigación se llevó a cabo bajo los criterios de este documento, respetando el
cronograma de actividades y el presupuesto establecido. Se llegó a la conclusión que
la aplicación del Last Planner System mejoró el cumplimiento de plazos de ejecución
del proyecto hospital de Ayabaca, Piura – 2022. Se recomendó que la empresa debe
seguir aplicando la Metodología Last Planner System en todo tipo de proyecto, con la
finalidad de que disminuyan sus costos operativos y mejore el tiempo de cumplimiento
de plazos de ejecución. | es_PE |
dc.description.abstract | This research study responds to the following research problem: What is the
implementation of the Last Planner System to improve compliance with the execution
deadlines of the Ayabaca hospital project, Piura - 2022? And its general objective is to
carry out the implementation of the Last Planner System to improve compliance with
the execution deadlines of the Ayabaca hospital project, Piura - 2022. and the general
hypothesis that was verified was: The implementation of the Last Planner System
significantly improves compliance with deadlines for execution of the Ayabaca Hospital
project, Piura - 2022. The research method is quantitative and longitudinal; type of
applied research; with an explanatory descriptive research level and non-experimental
design with a transversal nature. The sample is made up of the characterization of the
Hospital de Ayabaca - Piura project. For this, data collection techniques were used,
such as observation and documentary analysis that helped to tabulate the information
in Microsoft Excel software, where percentage information was obtained and plotted in
diagrams and tables. The research plan was carried out under the criteria of this
document, respecting the schedule of activities and the established budget. It was
concluded that the application of the Last Planner System improved compliance with
the execution deadlines of the Ayabaca hospital project, Piura - 2022. It was
recommended that the company continue to apply the Last Planner System
Methodology in all types of project, with the in order to reduce their operating costs and
improve the time of compliance with execution deadlines. | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVILP_036 | |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Sistema Last Planner | es_PE |
dc.subject | Planificación y Confiabilidad | es_PE |
dc.title | Implementación del Last Planner System para mejorar el cumplimiento de plazos de ejecución del proyecto Hospital de Ayabaca, Piura - 2022 | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0001-5207-4421 | es_PE |
renati.author.dni | 41617879 | |
renati.author.dni | 42012363 | |
renati.advisor.dni | 40534510 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Henriquez Ulloa, Paul | |
renati.juror | Durand Orellana, Roció | |
renati.juror | Perrigo Sarmiento, Félix | |
dc.publisher.country | PE | es_PE |