Show simple item record

dc.contributor.advisorMedina Carbajal, Lucio Sigifredo
dc.contributor.authorPérez Roncal, Frank Chellenko
dc.contributor.authorCueva Gavidia, Cristhian Enrique
dc.creatorPérez Roncal, Frank Chellenko
dc.date.accessioned2024-07-03T20:18:52Z
dc.date.available2024-07-03T20:18:52Z
dc.date.issued2024
dc.identifier.urihttps://hdl.handle.net/20.500.12759/32732
dc.description.abstractAnte el sistema de gestión convencional que se desarrolla en la ejecución de obras, se denotó diversos tipos de inconvenientes lo cual impide el óptimo desarrollo de la construcción de obras, es por ello que este análisis se enfoca en el mejoramiento de la productividad a través de la metodología Last Planner System en el mejoramiento del centro de especialización en informática de SENCICO, Trujillo. Se inició definiendo los procesos constructivos de las partidas de estructuras y al mismo tiempo clasificando los trabajos por trabajo productivo, trabajo contributario y trabajo no contributario, ya que con ello descubriremos y analizaremos las dificultades presentadas para desarrollar un buen trabajo en obra. Posteriormente, a través de los principios de sistema Last Planner se sectorizó el proyecto a analizar, se organizó el tren de actividades, plan maestro, LookAHead Planning y Weekly Planning para obtener un planeamiento de forma general que nos permita visualizar todas las partidas en lo largo de 10 meses con la finalidad principal de controlar la unidad de producción para la mejora continua obteniendo así, un incremento en la productividad de la ejecución de obra; el proyecto está incluido dentro de los planes intermedios y planes semanales que nos permitió controlar las unidades de producción Todo lo analizado tiene el propósito de la mejorar del desarrollo de las actividades del mejoramiento del centro de especialización en informática de SENCICO, Trujillo por lo cual se obtuvo que el Tiempo Productivo (TP) 42%, Tiempo Contributorio (TC) 47% Y Tiempo No Contributorio (TNC) 11% el cual indica que en promedio 15 días se tomó para realizar la construcción de la institución de manera convencional, mientras tanto, con la propuesta planteada inicialmente se lograría en 11 días la mejora de productividad tomando la construcción del mismo. Concluyendo así, que la metodología aplicada que el sistema propuesto benefició en el aspecto de tiempo y costo, logrando de esta forma un mayor rendimiento de productividad en la construcción de la Institución Educativaes_PE
dc.description.abstractGiven the conventional management system that is developed in the execution of works, various types of inconveniences were noted which prevent the optimal development of the construction of works, which is why this analysis focuses on improving productivity through the Last Planner System methodology in the improvement of the SENCICO computer science specialization center, Trujillo. It began by defining the construction processes of the structural items and at the same time classifying the work by productive work, contributory work and non-contributory work, since with this we will discover and analyze the difficulties presented to develop good work on site. Subsequently, through the principles of the Last Planner system, the project to be analyzed was sectored, the train of activities, master plan, LookAHead Planning and Weekly Planning were organized to obtain a general plan that allows us to visualize all the items throughout . of 10 months with the main purpose of controlling the production unit for continuous improvement, thus obtaining an increase in the productivity of the execution of work; The project is included in the intermediate plans and weekly plans that allow us to control the production units. Everything analyzed has the purpose of improving the development of the activities of the SENCICO computer science specialization center, Trujillo, for which it was obtained that the Productive Time (TP) 42%, Contributory Time (TC) 47% and Time Non-Contributory (TNC) 11% which indicates that on average 15 days were taken to carry out the construction of the institution in a conventional manner, meanwhile, with the proposal initially proposed, the improvement in productivity would be achieved in 11 days by taking the construction of the same . Thus concluding that the methodology applied that the proposed system benefited in the aspect of time and cost, thus achieving greater productivity performance in the construction of the Educational Institutiones_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada Antenor Orregoes_PE
dc.relation.ispartofseriesT_CIVIL_2521
dc.rightsinfo:eu-repo/semantics/closedAccesses_PE
dc.rights.urihttps://creativecommons.org/licenses/by/4.0/es_PE
dc.subjectLast Planner Systemes_PE
dc.subjectWeekly Planninges_PE
dc.subjectTiempo No Contributorioes_PE
dc.titleAplicación del Last Planner System para la mejora en la producción del mejoramiento del centro de especialización en informática de SENCICO, Trujilloes_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada Antenor Orrego. Facultad de Ingenieríaes_PE
thesis.degree.nameIngeniero Civiles_PE
thesis.degree.disciplineIngeniería Civiles_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.00es_PE
renati.advisor.orcidhttps://orcid.org/0000-0001-5207-4421es_PE
renati.author.dni48434528
renati.author.dni71482569
renati.advisor.dni40534510
renati.typehttps://purl.org/pe-repo/renati/type#tesises_PE
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.discipline732016es_PE
renati.jurorGeldres Sánchez, Carmen Lucía
renati.jurorPanduro Alvarado, Elka
renati.jurorVertiz Malabrigo, Manuel Alberto
dc.publisher.countryPEes_PE


Files in this item

Thumbnail
Thumbnail
Thumbnail

This item appears in the following Collection(s)

Show simple item record

info:eu-repo/semantics/closedAccess
Except where otherwise noted, this item's license is described as info:eu-repo/semantics/closedAccess