dc.description.abstract | En el ámbito de la construcción, la gestión eficiente de proyectos es crucial para
asegurar la calidad, minimizar costos y cumplir con los plazos establecidos. Sin
embargo, es común enfrentarse a discrepancias entre los planos y las
especificaciones técnicas, lo cual puede llevar a problemas significativos durante la
ejecución. Para abordar estos desafíos, se propone la adopción de la metodología
Building Information Modeling (BIM), que revoluciona la forma en que se planifica,
diseña y ejecuta la construcción.
BIM se fundamenta en la creación de modelos digitales tridimensionales que
integran información detallada sobre todos los aspectos del proyecto, desde la
arquitectura hasta las instalaciones eléctricas y sanitarias. Estos modelos permiten
una visualización precisa y una coordinación eficiente entre diferentes disciplinas,
identificando conflictos potenciales antes de la construcción física.
En esta investigación, se examinó el impacto de BIM en el proyecto
""Desembarcadero Pesquero Artesanal La Cruz"", ubicado en La Cruz, provincia de
Tumbes. Utilizando herramientas como Revit y Navisworks, El modelo BIM creado
ayuda a descubrir y resolver varias diferencias y conflictos entre los
diseños originales. Este estudio demuestra cómo BIM mejora la gestión del diseño,
reduce errores durante la construcción y optimiza el uso de recursos, contribuyendo
a la entrega de proyectos más eficientes y de mayor calidad.
Los resultados obtenidos subrayan la importancia de adoptar BIM como una
práctica estándar en la industria de la construcción. Al proporcionar una plataforma
integrada para la colaboración multidisciplinaria y la simulación virtual, BIM no solo
mejora la coordinación entre equipos de trabajo, sino que también promueve una
planificación más precisa y una ejecución más efectiva de proyectos.
En resumen, esta investigación sostiene que la implementación de BIM no solo
optimiza el proceso de construcción, sino que también fortalece la capacidad del
sector para enfrentar los desafíos actuales y futuros, asegurando así un desarrollo
sostenible y eficiente de infraestructuras. | es_PE |
dc.description.abstract | In the construction field, efficient project management is crucial to ensure quality,
minimize costs and meet established deadlines. However, it is common to face
discrepancies between plans and technical specifications, which can lead to
significant problems during execution. To address these challenges, the adoption of
the Building Information Modeling (BIM) methodology is proposed, which
revolutionizes the way construction is planned, designed and executed.
BIM is based on the creation of three-dimensional digital models that integrate
detailed information on all aspects of the project, from architecture to electrical and
sanitary installations. These models allow for accurate visualization and efficient
coordination between different disciplines, identifying potential conflicts before
physical construction.
In this research, the impact of BIM on the project ""Desembarcadero Pesquero
Artesanal La Cruz"" was examined, located in La Cruz, province of Tumbes. Using
tools such as Revit and Navisworks, the BIM model created helps to discover and
resolve various differences and conflicts between the original designs. This study
demonstrates how BIM improves design management, reduces errors during
construction and optimizes the use of resources, contributing to the delivery of more
efficient and higher quality projects.
The results obtained underline the importance of adopting BIM as a standard
practice in the construction industry. By providing an integrated platform for
multidisciplinary collaboration and virtual simulation, BIM not only improves
coordination between work teams, but also promotes more accurate planning and
more effective project execution.
In summary, this research argues that BIM implementation not only optimizes the
construction process, but also strengthens the sector's capacity to meet current and
future challenges, thus ensuring sustainable and efficient infrastructure
development. | es_PE |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVIL_2585 | |
dc.rights | info:eu-repo/semantics/closedAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.subject | Metrados | es_PE |
dc.subject | Modelado de Información de Construcción (BIM) | es_PE |
dc.title | Propuesta de implementación de la metodología BIM en el diseño del “Desembarcadero Pesquero Artesanal La Cruz”, departamento de Tumbes | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingenieria | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingenieria Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0002-8113-0610 | es_PE |
renati.author.dni | 74317271 | |
renati.author.dni | 71477690 | |
renati.advisor.dni | 41455986 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Sagastegui Plasencia, Fidel German | |
renati.juror | Vertiz Malabrigo, Manuel Alberto | |
renati.juror | Panduro Alvarado, Elka | |
dc.publisher.country | PE | es_PE |