dc.description.abstract | La presente tesis tuvo como objetivo elaborar la gestión del cronograma para la
construcción del canal revestido tramo II sector este del proyecto diques en la
quebrada el león ubicado en la ciudad de Trujillo, departamento de La Libertad; el
tipo de investigación de acuerdo con su orientación fue de carácter aplicativa y de
acuerdo con su técnica de contrastación fue descriptiva.
Para la gestión planteada en esta investigación, se aplicó la metodología establecida
por el Project Management Institute, más conocido como PMBOK, considerando
la sexta edición, donde se elaboró la planificación, el desarrollo y sobre todo el
control del cronograma hasta la culminación del proyecto, logrando mejorar el
plazo en comparación a la ejecución real del proyecto.
El proceso de gestión aplicado fue el siguiente; primero, se revisó todos los
informes mensuales de avance de obra entregados por el subcontratista, segundo,
seleccionamos el mes con mayor impacto de atraso para comenzar a desarrollar la
gestión del cronograma; tercero, para la planificación se realizó el acta de
constitución del proyecto; cuarto, teniendo el alcance definido se hizo una lista de
actividades e hitos; quinto, se elaboró el cronograma en el software Primavera P6
colocando los recursos y duraciones teniendo en cuenta las lecciones aprendidas
por parte del subcontratista y el juicio de expertos; por último se realizó el análisis
de valor ganado aplicando el SPI mes a mes, la cual nos ayudó a controlar el
cronograma hasta la culminación del proyecto. Las herramientas y técnicas
utilizadas fueron el juicio de expertos, las reuniones y el método de la ruta crítica.
Por otro lado, gracias a la metodología del PMBOK se logró obtener los objetivos
específicos planteados en el desarrollo de la investigación, así como la mejora del
cumplimiento de los plazos en comparación con la línea base final del proyecto.
Por lo que, la presente tesis será de suma importancia como antecedente para futuros
proyectos que aspiren a mejorar el logro de los plazos y mejora en el control de la
dirección de su proyecto | es_PE |
dc.description.abstract | This thesis aims to develop the schedule management for the construction of the
lined canal, section II, east sector, of the project Diques in Quebrada El León located
in Trujillo city, La Libertad department. The research is applied in nature according
to its orientation, and descriptive according to its validation technique.
For the management proposed in this research, the methodology established by the
Project Management Institute, commonly known as PMBOK, was applied,
considering the sixth edition. This involved planning, developing, and, above all,
controlling the schedule until the project's completion, achieving an improvement
in the timeline compared to the actual execution of the project.
The management process was as follows: first, all monthly progress reports
submitted by the subcontractor were reviewed; second, the month with the most
significant delay was selected to begin developing the schedule management; third,
a project charter was created for planning; fourth, with the scope defined, a list of
activities and milestones was developed; fifth, the schedule was created using
Primavera P6 software, incorporating resources and durations based on lessons
learned from the subcontractor and expert judgment; finally, earned value analysis
was performed using SPI month by month, which helped control the schedule until
the project's completion. The tools and techniques used included expert judgment,
meetings, and the critical path method. Additionally, thanks to the PMBOK
methodology, the specific objectives set out in the research development were
achieved, as well as improving compliance with deadlines compared to the project's
final baseline.
Therefore, this thesis will be of great importance as a precedent for future projects
aiming to improve deadline achievement and enhance project management control. | es_PE |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | M_INGE_242 | |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.subject | Gestión | es_PE |
dc.subject | Cronograma | es_PE |
dc.title | Gestión del cronograma para la construcción del canal revestido tramo II del proyecto diques en la quebrada el león, Trujillo | es_PE |
dc.type | info:eu-repo/semantics/masterThesis | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Escuela de Postgrado | es_PE |
thesis.degree.name | Maestro en Gerencia de la Construcción Moderna | es_PE |
thesis.degree.discipline | Maestría en Ingenieria | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.03 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0003-2612-3298 | es_PE |
renati.author.dni | 70655019 | |
renati.advisor.dni | 18074977 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#maestro | es_PE |
renati.discipline | 732207 | es_PE |
renati.juror | Gálvez Paredes, José Alcides | |
renati.juror | Vértiz Malabrigo, Manuel Alberto | |
renati.juror | Cerna Sánchez, Eduardo Elmer | |
dc.publisher.country | PE | es_PE |