dc.description.abstract | Durante el proceso de construcción en un proyecto de edificación, siempre se
encuentran diferentes tipos de deficiencias entre los planos y las especificaciones
técnicas. Estas deficiencias causan un impacto negativo durante la etapa de
construcción sobre los costos y los plazos en la ejecución del proyecto y con esto
afectan en la calidad del proyecto.
Para mitigar estos problemas, se plantea el uso de las herramientas de una
metodología la cual se basa en el uso de los modelos tridimensionales que nos
facilitara la visualización, estimación de materiales y la compatibilización en la etapa
de planificación. Mediante esta metodología se logró encontrar incompatibilidades e
interferencias y hacer una simulación del proceso constructivo.
En esta tesis, se utilizó los softwares especializados de la metodología BIM (Revit y
Naviswork), las cuales permitieron modelar las diferentes especialidades las cuales
son: Estructura, Arquitectura, Instalaciones eléctricas, Instalaciones sanitarias e
Instalaciones mecánicas, obteniendo como resultado 71 incompatibilidades e
interferencias.
El proyecto escogido como muestra representativa, fue el: “Conjunto residencial Paseo
Victoria” ubicado en el distrito de Chorrillo en la ciudad de Lima.
Finalmente, los resultados obtenidos, se realizó una comparación mediante gráficos
estadísticos de lo obtenido usando las herramientas de la metodología BIM.
En conclusión, podemos decir que Building Information Modeling optimiza el proceso
de diseño en la construcción, fomenta una buena práctica constructiva y permite que
el proyecto sea exitoso por permitir un mejor control e identificación de errores
anticipados, usando un modelo virtual que permita el planteamiento de soluciones
anticipadas para luego en la construcción real, ya no haya retrasos, en donde el
contratista va a aumentar su eficiencia en la programación, producción y calidad de
construcción.“ | es_PE |
dc.description.abstract | During the construction process in a building project, there are always different types
of deficiencies between the plans and the technical specifications. These deficiencies
cause a negative impact during the construction phase on the costs and deadlines in
the execution of the project and thus affect the quality of the project.
To mitigate these problems, the use of the tools of a methodology is proposed, which
is based on the use of three-dimensional models that will facilitate the visualization,
estimation of materials and compatibility in the planning stage. Through this
methodology it was possible to find incompatibilities and interferences and make a
simulation of the constructive process.
In this thesis, specialized softwares of the BIM methodology (Revit and Naviswork)
were used, which allowed us to model the different specialties which are: Structure,
Architecture, Electrical Installations and Sanitary Facilities, resulting in 71
incompatibilities and interferences.
The project chosen as a representative sample was: ““Paseo Victoria residential
complex““ located in the district of Chorrillo in the city of Lima.
Finally, the results obtained, a comparison was made through statistical graphs of what
was obtained using the tools of the BIM methodology.
In conclusion, we can say that Building Information Modeling optimizes the design
process in construction, promotes a good constructive practice and allows the project
to be successful by allowing a better control and identification of anticipated errors,
using a virtual model that allows the approach of anticipated solutions for later in the
real construction, there are no delays, where the contractor will increase its efficiency
in programming, production and construction quality. | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_ING.CIVIL_758 | |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Incompatibilidades e interferencias | es_PE |
dc.title | Propuesta de implementación de la tecnología BIM como herramienta en la planificación de la construcción en la segunda etapa del conjunto residencial paseo victoria en la ciudad de lima - chorrillos | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | |
dc.publisher.country | PE | es_PE |