Mostrar el registro sencillo del ítem
Gestión de riesgos en el proyecto residencial Sol de Chan-Chan, ciudad de Trujillo
dc.contributor.advisor | Vejarano Geldres, Augusto Alejandro | |
dc.contributor.author | León Loyola, Ronald Humberto | |
dc.contributor.author | Mariños Lozada, Verrys Nells | |
dc.creator | León Loyola, Ronald Humberto | |
dc.date.accessioned | 2015-03-05T22:22:20Z | |
dc.date.available | 2015-03-05T22:22:20Z | |
dc.date.issued | 2014 | |
dc.identifier.uri | https://hdl.handle.net/20.500.12759/613 | |
dc.description.abstract | En los últimos años, la industria de la construcción en Trujillo se ha intensificado de una manera sin precedentes, debido principalmente a iniciativas políticas y a un escenario favorable de la economía. Sin embargo, esto no quiere decir que la construcción haya mejorado. Actualmente, aún existen muchas deficiencias en los proyectos de construcción en nuestra zona, las cuales se traducen en pérdidas económicas. Al mismo tiempo, muchos de ellos no llegan a cumplir los objetivos para los que fueron originalmente planteados. Teniendo en cuenta lo mencionado, surge la necesidad por parte de las empresas constructoras de nuestra zona llevar a cabo un eficiente manejo de los riesgos e incertidumbres que perjudican la ejecución de sus proyectos. En este contexto, la planificación de gestión de riesgos, como medio de optimización de proyectos, toma un renovado protagonismo y se convierte en una necesidad. Esta investigación pretende definir y establecer a la Gestión de Riesgos como un sistema estratégico de técnicas y herramientas útiles que permitan un manejo de los riesgos e incertidumbres que perjudican la ejecución y los objetivos del proyecto., con la finalidad de optimizar el costo, plazo, calidad y seguridad, así como asegurar la rentabilidad de la empresa constructora que la aplica. El desarrollo del marco teórico y los conocimientos obtenidos nos permitieron establecer nuestra metodología de trabajo que comprende: la identificación de los riesgos, el análisis cualitativo y cuantitativo, la evaluación y plan de respuesta a los riesgos y finalmente las conclusiones y recomendaciones. Para llevar a cabo la identificación de los riesgos se determinaron las actividades implicadas que van desde la aprobación por parte del INC y la Municipalidad de Huanchaco para iniciar la ejecución del proyecto hasta el levantamiento de observaciones presentadas por los propietarios de las viviendas al área de postventa. Determinadas las actividades, se realizaron entrevistas con el personal técnico y profesional involucrado al proyecto, identificando los riesgos en este. Los mismos integrantes participaron de las encuestas elaboradas, las cuales consistían en calificar la probabilidad de ocurrencia de los riesgos así como el impacto de estos, de acuerdo a la escala fijada en cada uno de ellos. El análisis cualitativo se desarrolló aplicando la matriz de impacto y probabilidad, encontrando de esta manera el nivel de riesgo que está definido desde muy bajo hasta muy alto. El análisis cuantitativo plasma en porcentajes el puntaje asignado a los riesgos por cada uno de los encuestados, tanto para la probabilidad como el impacto. Habiendo identificado y analizado los riesgos, se elaboró un plan de respuesta a estos, con la finalidad de reducir los riesgos en su futura aplicación. En el plan de respuesta se definieron las estrategias a implementar frente a los riesgos así como las tareas específicas para cumplir dichos propósitos. Por último, el objetivo del plan de respuesta a los riesgos propuesto producto de la investigación radica en ser reutilizada a posteridad porque es aplicable, y a la vez ofrezca soporte para la gestión de riesgos en el análisis, seguimiento y monitoreo fundamentado en un sistema colaborativo y actualizado. | es_PE |
dc.description.abstract | In recent years, the construction industry in Trujillo has intensified in an unprecedented way, mainly due to policy initiatives and a favorable scenario of the economy. However, this doesn’t mean that construction has improved. Currently, there are still many deficiencies in construction projects in our area, which result in economic losses. At the same time, many of them fail to meet the objectives for which they were originally elaborated. Considering this, the need arises by construction companies in our area to conduct an effective management of risks and uncertainties that harm the execution of their projects. In this context, risk management planning, as a means of optimizing projects, takes a renewed importance and becomes a necessity. This research aims to define and establish Risk Management as a strategic set of techniques and tools that allow management of risks and uncertainties that harm the execution and project objectives, in order to optimize the cost, schedule, quality and safety, and ensure profitability of the construction company that applies. The development of the theoretical framework and knowledge obtained allowed us to establish our work methodology that includes: identifying risks, qualitative and quantitative analysis, assessment and response plan risks and finally the conclusions and recommendations. To carry out the identification of the risks, involved activities ranging from approval by the INC and the Municipality of Huanchaco were determined to start the project until the suppression of comments submitted by homeowners in aftersales area. Once determined the activities, interviews were conducted with the technical and professional staff involved in the project, identifying risks in this. The same members participated in the elaborate surveys, which were to rate the likelihood of the risks and the impact of these, according to the scale fixed in each of them. The qualitative analysis was developed using the matrix of impact and probability, finding in this way the level of risk that is defined from very low to very high. Quantitative analysis translates to percentage the score assigned to the risks for each of the respondents, both the probability and impact. Having identified and analyzed the risk, a response plan was developed, in order to reduce risks in future implementation. In response plan were defined the strategies against the risks and the specific tasks to fulfill those purposes. Finally, the objective of the target risk response plan product of the research lies in being reused to posterity because it is applicable, while offering support for risk management analysis, tracking and monitoring based on a collaborative and updated system. | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Gestión de riesgo | es_PE |
dc.subject | Proyecto residencial | es_PE |
dc.subject | Sol de Chan Chan | es_PE |
dc.title | Gestión de riesgos en el proyecto residencial Sol de Chan-Chan, ciudad de Trujillo | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | |
dc.publisher.country | PE | es_PE |
Ficheros en el ítem
Este ítem aparece en la(s) siguiente(s) colección(es)
-
Ingeniería Civil [1260]