Show simple item record

dc.contributor.advisorVértiz Malabrigo, Manuel
dc.contributor.authorSolón Haro, Luis Alberto
dc.creatorSolón Haro , Luis Alberto
dc.date.accessioned2020-09-14T22:10:24Z
dc.date.available2020-09-14T22:10:24Z
dc.date.issued2020
dc.identifier.urihttps://hdl.handle.net/20.500.12759/6554
dc.description.abstractEl proyecto tiene por objetivo evacuar las aguas discurridas presentes en la Mina Huaron, para así poder acceder a las reservas y recursos minerales existentes debajo, específicamente al nivel 100 de la Zona Norte y Sur. Como punto de partida se hizo un estudio hidrogeológico para determinar el caudal a considerar en el sistema de bombeo. Para llegar al Nv. 100 se ejecutarán dos rampas de profundización, la Rp 857 con dirección Norte-Sur y la Rp 871 con dirección Sur-Norte, una vez que con ambas se llegue al nivel 100 mediante un by pass se integrarán ambas rampas, y se construirá la cámara de bombeo principal en donde se bombeará el agua desde el Nv. 100 hasta el Nv. 250, para ello, también se dispuso la implementación de un circuito de ventilación que tendrá un direccionamiento de Norte a Sur. Se considera un sistema de bombeo de 01 etapa, como flujo nominal en cada línea de 120 l/s y flujo de diseño de 360 l/s para cada línea, con 03 tuberías independientes de 10” HDPE SDR-11, 03 bombas centrifugas (Seleccionadas para 120 l/s- ADT 90 m)- 02 bombas operando en paralelo con 01 bomba en stand by. En la profundización de la rampa 857 se ha considerado el avance en 5 etapas de bombeo, teniendo en cuenta algunos parámetros hidráulicos para el cálculo del Hp requerido para la bomba, en la etapa final de bombeo se construirá una cámara de bombeo alternativo con capacidad de 400l/s (cola de bombeo por debajo del Nv 100). En la profundización de la rampa 871 se han considerado la construcción de 4 cámaras de Bombeo en la proyección de la rampa y una cámara auxiliar de bombeo en la cota del nivel 100, el circuito de bombeo será en cascada, cada cámara estará espaciada a 100m, de tal manera que, llegando al Nv 100 se construirá una poza de bombeo principal bombeando el agua desde el Nv 100 hasta el Nv 250 a través de una Raise Borer de 152 m y 10 pies de diámetro. vi Finalmente, el proyecto contempla el cálculo de dos sedimentadores en el nivel 100 para un caudal de 400 l/s, canal de recolección de agua, pozas de agua clarificada y patio de bombas. Las pozas de sedimentación serán diseñadas para que la limpieza se realice con equipo (Scoop).es_PE
dc.description.abstractThe objective of the project is to evacuate the discharged waters present in the Huaron Mine, in order to gain access to the existing mineral reserves and resources below, specifically at level 100 of the North and South Zone. As a starting point, a hydrogeological study was carried out to determine the flow to consider in the pumping system. To reach level 100, two deepening ramps will be executed, Rp 857 with North-South direction and Rp 871 with South-North direction, once both reach level 100 through a bypass, both ramps will be integrated, and The main pumping chamber will be built where the water will be pumped from level 100 to level 250, for this, the implementation of a ventilation circuit that will have a North-South direction will also be arranged. A 01 stage pumping system is considered, as nominal flow in each line of 120 l / s and design flow of 360 l / s for each line, with 03 independent pipes of 10 ““HDPE SDR-11, 03 centrifugal pumps (Selected for 120 l / s- ADT 90 m) - 02 pumps operating in parallel with 01 pump in standby. In the deepening of ramp 857, the progress in 5 pumping stages has been considered, taking into account some hydraulic parameters for the calculation of the Hp required for the pump. In the final pumping stage, an alternative pumping chamber with the capacity of 400l / s (pumping tail below Lv. 100). In the deepening of ramp 871, the construction of 4 pumping chambers in the projection of the ramp and an auxiliary pumping chamber at the level 100 level have been considered, the pumping circuit will be cascaded, each chamber will be spaced at 100m In such a way that, arriving at Lv 100, a main pumping pool will be built by pumping the water from Lv 100 to Lv 250 through a 152 m and 10 ft diameter Raise Borer. Finally, the project includes the calculation of two settlers at level 100 for a flow of 400 l / s, a water collection channel, clarified water pools and a pump yard. The viii sedimentation pools will be designed so that the cleaning is carried out with equipment (Scoop)en_US
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada Antenor Orregoes_PE
dc.relation.ispartofseriesT_ING.CIVIL_1851
dc.rightsinfo:eu-repo/semantics/closedAccesses_PE
dc.sourceUniversidad Privada Antenor Orregoes_PE
dc.sourceRepositorio Institucional - UPAOes_PE
dc.subjectAguases_PE
dc.subjectBombeoes_PE
dc.titleDiseño de un sistema de bombeo para evacuar las aguas discurridas en la rampa de profundización al nivel 100 de la Minera Huarónes_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.grantorUniversidad Privada Antenor Orrego. Facultad de Ingenieríaes_PE
thesis.degree.nameIngeniero Civiles_PE
thesis.degree.disciplineIngeniería Civiles_PE


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record