Mostrar el registro sencillo del ítem
Aplicación del Last Planner System para incrementar la productividad en la construcción del colegio San Ramón, distrito de Chulucanas - Piura
dc.contributor.advisor | Panduro Alvarado, Elka | |
dc.contributor.author | Astocondor Castro, Amalia Lucia | |
dc.contributor.author | Gonzáles Callirgos, Piero Rennato | |
dc.creator | Astocondor Castro, Amalia Lucia | |
dc.date.accessioned | 2022-06-23T00:18:52Z | |
dc.date.available | 2022-06-23T00:18:52Z | |
dc.date.issued | 2022 | |
dc.identifier.uri | https://hdl.handle.net/20.500.12759/9109 | |
dc.description.abstract | Actualmente, en el rubro de la construcción aún no se presentan en su totalidad la obtención de las nuevas mejoras debido a la falta de una metodología, se han ido alcanzando metas no deseadas y ocasionando a su vez actividades que no se cumplan desde su planificación inicial hasta su planificación final. Ante esta problemática, tuvo como planteamiento del problema a la siguiente pregunta ¿En qué medida aplicando el Last Planner System se incrementará la productividad en la construcción del colegio San Ramón, distrito de Chulucanas- Piura? Y a su vez se confirmó y se demostró el cumplimiento de la hipótesis propuesta mediante el estadístico SPS para así poder corroborar que el nivel de significancia (z) sea menor al grado de riesgo considerado por el investigador, es decir menor al 5% y dar aceptación a la hipótesis alterna y rechazar una supuesta hipótesis nula. Según arquitectura, este colegio consta con 5 Bloques de nivel Inicial,2 Bloques de nivel Primario,5 Bloques de nivel Secundario y entre otros bloques de servicios como cafetería, vestidores, plataformas deportivas. Los bloques evaluados con el sistema LPS fueron el B01-B04-B05A-B05B, primer y segundo nivel y como muestra se consideraron las partidas de estructuras, arquitectura, eléctrica y sanitaria. sé estimaron aproximadamente 351 subpartidas, las cuales fueron repartidas de forma proporcional para su elaboración, es decir 159 subpartidas para estructuras,97 para arquitectura,49 para II.EE y 46 para II. SS correspondientemente, para obtener el tamaño de la muestra de estudio se basó en la formula estadística de la variable cualitativa para una muestra con población finita, el tipo y método de muestreo es alusivo a un no probabilístico acorde al criterio del investigador y se consideró un muestreo por cuotas ya que las características de las muestras fueron las mismas que en la población. La presente tesis tiene como objetivo principal la aplicación del Last Planner en la construcción del colegio San Ramón , con esta finalidad según su diseño de contrastación se consideró una investigación preexperimental porque a partir de la muestra representativa se realizó un análisis observacional antes y después de haberse aplicado la variable a desarrollarse. Según el alcance de esta investigación VIII es aplicativo, porque se encarga de desarrollar soluciones basadas en el objeto de estudio para así poder ser efectuadas, reduciendo las ineficiencias y variabilidades en la productividad del colegio San Ramón, según técnica de contrastación es de tipo cualitativo porque se entregara un reporte final acerca de los porcentajes de cumplimiento sobre aquellas partidas que se realizaron o no, y según su fuente es considerada de campo porque la recolección de datos se hizo directamente en el lugar de estudio. Las herramientas de este sistema fueron necesarias para su desarrollo dentro de la constructora (Plan Maestro, Sectorización,Calculo de los trenes de trabajo por dia y por sector acompañado del dimensionamiento de cuadrillas ,Tren de Actividades, Lookhead Intermedio,la Implementación de buffers, Plan Semanal, Análisis de restricciones, Porcentaje de Plan Cumplido, Causas de no Cumplimiento,Informe de producción). Todos estos elementos nos ayudaron a lograr un mejor progreso incrementando así su productividad en la construcción, por tal motivo como primer paso se realizó una programación maestra con una vista general y real del proyecto referente a las 23 semanas de ejecución, como segundo paso se realizó un Pull Session para evaluar y eliminar posible factores inoportunos que podrían presentarse en el final como en el inicio de su programación, como tercer paso se efectuó una sectorización y una compensación de metrados para cada bloque y nivel, como cuarto paso se efectuó el calculo de los trenes de trabajo y tren de actividades secuencial,como quinto y sexto paso se desarrolló un Lookhead Planning y un plan semanal acompañado de un análisis de restricciones para cada semana de ejecución y como último paso se determinó los PPC para medir la fiabilidad de la planificación,los CNC,los IP y se comparó si beneficio o no la planificación en la obra. Uno de los resultados encontrados al efectuar esta metodología es poder reconocer aquellas causales por el cual no se dieron cumplimiento de las actividades según acordaba la programación.Durante su ejecución los bloques 01, 04 y 05 fueron reagrupados en sectores donde se encontraron 7 CNC , los cuales fueron visualizados en un diagrama de pareto y gráficos de las 23 semanas. Las CNC IX fueron ocasionadas por parte de la logística , subcontratista , administrativo, ejecución ,cliente o supervisión , equipos ,externo. Estas causales han sido consideradas como las más habituales en obra y a su vez fueron determinadas como actividades que requieren mayor supervisión en el proyecto para después optar por eliminarlas o minimizarlas según corresponda. Luego en su interpretación se pudo decir que desde la 01 semana hasta la semana 23 existió un aumento minucioso en su porcentaje del plan cumplido semanal, superando lo proyectado y cumpliendo así con los plazos establecidos. además, existió mejoras en la planificación y control de obra aumentado el % de confiabilidad de las programaciones y alcanzando un 92.20 %de PPC promedio, el cual es conforme en su avance. La aplicación del Last Planner System permitió contribuir con el incremento de la productividad a un 17.2 %, por ende se pudo confirmar ser una programación eficaz. Esto garantizó que alcance un PPC promedio de 92.2 % de confiabilidad. La empresa Perez y Castro obtuvo una rentabilidad de 8.11 % en la ejecucion en las partidas. En Muros Reforzado se representa la cantidad de S/8,768.28 ; en la partidas de las Vigas, el monto de S/15,789.15 y S/ 1,787.63 en la partida de Losas Así mismo se pudo confirmar la metodología LPS empleo menos HH para la misma sub partidas siendo más rentable al compararlo con el uso tradicional que emplean varias empresas además se calculó el índice de productividad para las partidas de acero, encofrado y concreto. Finalmente se realizó una evaluación con respecto al tiempo de construcción resultando que esta metodologia fue conveniente y eficaz debido que la obra se concluyo en 166 dias calendarios teniendo 14 dias calendarios de ganancias que equivale el 7.77% lo cual se pudo confirmar que los buffer de tiempo si ayudaron a la programación en efectuarlo mucho más antes del tiempo establecido, alcanzando así mejoras en la programación. | es_PE |
dc.description.abstract | Currently, in the field of construction, the obtaining of new improvements is not yet presented in its entirety due to the lack of a methodology, they have been achieved by reaching undesired goals and in turn causing activities that are not fulfilled from their initial planning. until its final planning. Faced with this problem, he had as a problem statement the following question: To what extent will productivity be increased in the construction of the San Ramón school, district of Chulucanas-Piura, by applying the Last Planner System? And in turn, it was confirmed and compliance with the proposed hypothesis was found through the SPS statistic in order to corroborate that the level of significance (z) is less than the degree of risk considered by the researcher, that is, less than 5% and give acceptance of the alternative hypothesis and rejection of a supposed null hypothesis. According to architecture, this school consists of 5 Blocks of Initial level, 2 Blocks of Primary level, 5 Blocks of Secondary level and among other blocks of services such as cafeteria, dressing rooms, sports platforms. The blocks evaluated with the LPS system were B01-B04-B05A-B05B, first and second level and as a sample the items of structures, architecture, electrical and sanitary are considered. I know approximately 351 subheadings were estimated, which were distributed proportionally for their preparation, that is, 159 subheadings for structures, 97 for architecture, 49 for II.EE and 46 for II. SS correspondingly, to obtain the size of the study sample, it was based on the statistical formula of the qualitative variable for a sample with a finite population, the type and method of the sample is allusive to a non-probabilistic according to the criteria of the researcher and a quota sample since the characteristics of the samples were the same as in the population. The main objective of this thesis is the application of the Last Planner in the construction of the San Ramon school. For this purpose, according to its contrasting design, it was considered a pre-experimental investigation because, based on the representative sample, an observational analysis was carried out before and after having applied the variable to be developed. According to the scope of this research, XI it is applicative, because it is in charge of developing solutions based on the object of study in order to be carried out, reducing inefficiencies and variability in the productivity of the San Ramon school, according to the contrasting technique, it is of a qualitative type because it is will deliver a final report about the percentages of compliance on those items that were made or not, and according to its source it is considered field because the data collection was done directly in the place of study. The tools of this system were necessary for its development within the construction company (Master Plan, Sectorization, Calculation of work trains per day and per sector accompanied by the dimensioning of crews, Activity Train, Intermediate Lookhead, Implementation of buffers, Plan Weekly, Analysis of restrictions, Percentage of Complied Plan, Causes of Non-Compliance, Production Report). All these elements helped us to achieve better progress, thus increasing its productivity in construction, for this reason, as a first step, a master programming was carried out with a general and real view of the project referring to the 23 weeks of execution, as a second step it was carried out a Pull Session to evaluate and eliminate possible inopportune factors that could appear at the end as well as at the beginning of its programming, as a third step, a sectorization and a compensation of meters for each block and level were carried out, as a fourth step, the calculation of the work trains and the sequential activity train, as the fifth and sixth step, a Lookhead Planning and a weekly plan were developed, accompanied by an analysis of restrictions for each week of execution, and as a last step, the PPCs were determined to measure the reliability of the planning. , the CNC, the IP and it was compared if it benefited or not the planning in the work. One of the results found when carrying out this methodology is to be able to recognize those causes for which the activities were not fulfilled according to the programming. During its execution, blocks 01, 04 and 05 were regrouped into sectors where 7 CNC were found, the which were visualized in a Pareto diagram and graphs of the 23 weeks. The CNC were caused by the logistics, subcontractor, administrative, execution, client or supervision, equipment, external. These causes have been considered the most common on site and, in turn, were determined as XII activities that require greater supervision in the project and then choose to eliminate or minimize them as appropriate. Then in its interpretation it could be said that from week 01 to week 23 there was a detailed increase in the percentage of the weekly plan fulfilled, exceeding what was projected and thus meeting the established deadlines. In addition, there were improvements in the planning and control of the work, increasing the % of reliability of the schedules and reaching 92.20% of the average PPC, which is consistent with its progress. The application of the Last Planner System managed to contribute to the increase in productivity to 17.2%, so it could be confirmed to be an effective schedule. This ensured that it achieved an average PPC of 92.2% reliability. The company Perez y Castro obtained a return of 8.11% in the execution of the games. In Reinforced Walls, the amount of S/8,768.28 is represented; in the Beams item, the amount of S/ 15,789.15 and S/ 1,787.63 in the Slabs item Likewise, it was possible to confirm the LPS methodology, employment less HH for the same sub items, being more profitable when compared with the traditional use used by several companies, in addition, the productivity index was calculated for the items of steel, formwork and concrete. Finally, an evaluation was made regarding the construction time, resulting in this methodology being convenient and effective because the work was completed in 166 calendar days, having 14 calendar days of earnings, which is equivalent to 7.77%, which confirmed that the time buffers if they helped the programming in doing it much more before the established time, thus achieving improvements in the programming. | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVILP_025 | |
dc.rights | info:eu-repo/semantics/closedAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Productividad | es_PE |
dc.subject | Subpartidas | es_PE |
dc.title | Aplicación del Last Planner System para incrementar la productividad en la construcción del colegio San Ramón, distrito de Chulucanas - Piura | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0003-4866-8707 | es_PE |
renati.author.dni | 71926642 | |
renati.author.dni | 75104297 | |
renati.advisor.dni | 18081570 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Vejarano Geldres, Alejandro | |
renati.juror | García Rivera, Juan | |
renati.juror | Durand Orellana, Roció del Pilar | |
dc.publisher.country | PE | es_PE |
Ficheros en el ítem
Este ítem aparece en la(s) siguiente(s) colección(es)
-
Ingeniería Civil [1260]