dc.description.abstract | La presente tesis titulada “IMPLEMENTACIÓN DE MATRIZ IPERC,
ESTÁNDAR DE TRABAJO SEGURO Y PLAN DE EMERGENCIA EN UN
PROYECTO DE MEJORAMIENTO DE UN CAMINO VECINAL EN JAÉN,
CAJAMARCA”, elaborada por los bachilleres Armas Franco Jesse Joe y
Chuquimia Bieli-Bianchi Kenti Marcelo, asesorados por el Ing. Jorge Antonio Vega
Benites, especialista en el área de la investigación. El objetivo principal es
implementar una matriz Iperc, estándar de trabajo seguro y plan de emergencia
en un proyecto de mejoramiento de un camino vecinal en Jaén, Cajamarca.
La población de la investigación son todos los proyectos que se están
ejecutando en el departamento de Cajamarca y la muestra a investigar es en el
proyecto de mejoramiento de un camino vecinal entre el Cruce Puente y el Cruce
Lanchema en Jaén, Cajamarca donde se implementará la matriz Iperc, estándar
de trabajo seguro y plan de emergencia.
Identificamos los peligros y riesgos de distintas actividades que se
realizarán en las partidas del proyecto mediante un formato creado por los
tesistas únicamente para la investigación. Estas actividades son Movilización y
Desmovilización de Equipo, Mantenimiento de tránsito temporal y seguridad vial,
Acceso a canteras Dme, Plantas fuentes de agua, Excavación para
explanaciones, Perfilado y compactado en zona de corte, Mejoramiento de suelos,
Limpieza de cauces encauzamiento, Excavación para estructuras en material
común en seco, Demolición de estructuras, Relleno para estructuras con material
propio, Concreto clase c (f'c=280 kg/cm2), Encofrado y desencofrado, Acero de
refuerzo, Sub base granular (con material propio), Base granular, Imprimación
asfáltica, Slurry seal e= 10mm. Finalmente analizaremos y evaluaremos estos
riesgos identificados a fin de proponer medidas de control para que mitigar las
consecuencias de estas. Posteriormente elaboraremos la propuesta de matriz
Iperc, estándar de trabajo seguro de las partidas del proyecto y plan de
emergencia. | es_PE |
dc.description.abstract | This thesis entitled ““IMPLEMENTATION OF THE IPERC MATRIX, SAFE
WORK STANDARD AND EMERGENCY PLAN IN A PROJECT TO IMPROVE A
NEIGHBORHOOD ROAD IN JAÉN, CAJAMARCA““, prepared by the high school
graduates Armas Franco Jesse Joe and Chuquimia Bieli-Bianchi Kenti Marcelo,
advised by Ing. Jorge Antonio Vega Benites, specialist in the research area. The
main objective is to implement an Iperc matrix, safe work standard and emergency
plan in a neighborhood road improvement project in Jaén, Cajamarca.
The population of the investigation are all the projects that are being
executed in the department of Cajamarca and the sample to be investigated is in
the improvement project of a local road between the Cruce Puente and the Cruce
Lanchema in Jaén, Cajamarca where the matrix will be implemented. Iperc, safe
work standard and emergency plan.
We identify the dangers and risks of different activities that will be carried
out in the project items through a format created by the thesis students solely for
research. These activities are Mobilization and Demobilization of Equipment,
Maintenance of temporary traffic and road safety, Access to Dme quarries, Water
source plants, Excavation for leveling, Profiling and compacting in the cutting
zone, Soil improvement, Cleaning of channeling channels, Excavation for
Structures in dry common material, Demolition of structures, Filling for structures
with own material, Concrete class c (f'c=280 kg/cm2), Formwork and stripping,
Reinforcing steel, Granular sub-base (with own material), Base granular, asphalt
primer, slurry seal e= 10mm. Finally, we will analyze and evaluate these identified
risks in order to propose control measures to mitigate their consequences.
Subsequently, we will prepare the Iperc matrix proposal, a safe work standard for
the project items and an emergency plan | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVIL_2103 | |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Matriz | es_PE |
dc.subject | Emergencia | es_PE |
dc.title | Implementación de Matriz Iperc, estandar de trabajo seguro y plan de emergencia en un proyecto de mejoramiento de un camino vecinal en Jaén, Cajamarca | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0002-8113-0610 | es_PE |
renati.author.dni | 75233924 | |
renati.author.dni | 71198626 | |
renati.advisor.dni | 41455986 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Vertiz Malabrigo, Manuel | |
renati.juror | Vargas López, Segundo Alfredo | |
renati.juror | Perrigo Sarmiento, Felix | |
dc.publisher.country | PE | es_PE |