dc.description.abstract | El objetivo principal de este estudio es proponer un sistema de control de
actividades, que brinde un modo de trabajar donde la prioridad se enfoque en la
calidad del resultado y no en entregables, este proyecto se desglosa bajo la Guía
PMBOK y se aplican todas las fases y herramientas, que están en los alineamientos
de esta metodología.
El cronograma de actividades en el proyecto “Aseguramiento de la calidad
durante la ejecución del mejoramiento del emisor de Paiján bajo la metodología del
PMBOK”, basándonos en proyectos que se hayan desarrollado bajo la influencia de
este sistema y que su implementación tanto como en los resultados haya sido exitosa.
formas de trabajar por lo que la entrega de productos se centra más en
resultados que en entregables
El sistema acelera la competitividad entre los proyectos al brindar accesibilidad
y orientación a diversos arquetipos de control de calidad de gestión que no están
preparados para aplicar las nuevas tecnologías.
Por lo cual, esta metodología nos demuestra la aplicabilidad y buenos
resultados como consecuencia primordial.
El control de cronograma es cada vez más importante en la construcción de
mejoramiento del emisor de Paiján, para mejorar la competitividad entre los proyectos
ingenieriles. Esta importancia se manifiesta de muchas maneras, pero quizás uno de
los más destacados es nuestro papel clave en la construcción de relaciones con
nuestros proveedores. Hoy en día, la nueva función que asume la gestión de costes
en las empresas de saneamiento u cualquier otro rubro; es encontrar estrategias de
valor añadido, gestionar los recursos de los suministros y conectar la cadena de valor
corporativa con la cadena de valor de los proveedores. La industria del saneamiento
tiene más opciones para mejorar la gestión logística a través la gestión adecuada de
los recursos, la reducción de costos e implementación de nuevas herramientas para
mejorar significativamente las estrategias competitivas dentro de su ámbito de
necesidad.
Los Principios capturan y resumen el propósito de las prácticas y funciones de
gestión de proyectos adaptables o con visión de futuro. Esta guía basada en principios
cumple con la nueva versión de los Estándares de Programa, Portafolio y Gestión de
Riesgos del PMI. Este nuevo estándar y las pautas de gestión de proyectos no
viii
contradicen las versiones anteriores basadas en procesos. La versión anterior sigue
siendo muy útil y relevante para determinar y evaluar las habilidades y metodologías
de gestión de proyectos y establecer metodologías adaptadas al proceso. Otro cambio
importante es la visión sistemática de la gestión de proyectos. Esto inicia con un
enfoque sistemático de la propuesta de valor en el estándar y una visión sistemática
del contenido de la guía. Este estándar enfatiza que los proyectos no solo producen
productos, sino resultados que agregan valor a la organización y sus partes
interesadas. La vista del sistema transforma los dominios de conocimiento en ocho
dominios de entrega de proyectos. Un desempeño dominante es un conjunto de
actividades que son críticas para la entrega efectiva de los entregables de un
proyecto.
Finalmente, esta investigación se orienta a presentar los resultados de
implementar varias herramientas del sistema de control de calidad propuestos en la
construcción para determinar el comportamiento de la obra en el tiempo que se
programa cuando se aplica este sistema y resaltar los beneficios que trae consigo. | es_PE |
dc.description.abstract | The main objective of this study is to propose an activity control system, which
provides a way of working where the priority is focused on the quality of the result and
not on deliverables, this project is broken down under the PMBOK Guide and all
phases are applied. and tools, which are in alignment with this methodology.
The schedule of activities in the project ““Quality assurance during the execution
of the improvement of the Paiján emitter under the PMBOK methodology““, based on
projects that have been developed under the influence of this system and that its
implementation as well as the results has been successful.
ways of working so that the delivery of products focuses more on results than on
deliverables
The system accelerates competitiveness among projects by providing
accessibility and guidance to various management quality control archetypes that are
not prepared to apply new technologies.
Therefore, this methodology shows us the applicability and good results as a
primary consequence.
Schedule control is increasingly important in the construction of improvement of
the Paiján emitter, to improve competitiveness among engineering projects. This
importance manifests itself in many ways, but perhaps one of the most prominent is
our key role in building relationships with our suppliers. Today, the new function
assumed by cost management in sanitation companies or any other item; is to find
value-added strategies, manage supply resources and connect the corporate value
chain with the suppliers' value chain. The sanitation industry has more options to
improve logistics management through the proper management of resources, cost
reduction and implementation of new tools to significantly improve competitive
strategies within its scope of need.
The Principles capture and summarize the purpose of forward-thinking or
adaptable project management practices and functions. This principles-based
guidance complies with the new version of PMI's Program, Portfolio and Risk
Management Standards. This new standard and project management guidelines do
x
not contradict previous process-based versions. The previous version is still very
useful and relevant for determining and evaluating project management skills and
methodologies and establishing methodologies adapted to the process. Another
important change is the systematic view of project management. This starts with a
systematic approach to the value proposition in the standard and a systematic view of
the guideline content. This standard emphasizes that projects not only produce
products, but results that add value to the organization and its stakeholders. The
system view transforms the knowledge domains into eight project delivery domains. A
performance override is a set of activities that are critical to the effective delivery of
project deliverables.
Finally, this research is oriented to present the results of implementing various
tools of the quality control system proposed in the construction to determine the
behavior of the work in the time that is scheduled when this system is applied and
highlight the benefits that it brings | en_US |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVIL_2202 | |
dc.rights | info:eu-repo/semantics/closedAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.source | Universidad Privada Antenor Orrego | es_PE |
dc.source | Repositorio Institucional - UPAO | es_PE |
dc.subject | Emisor | es_PE |
dc.subject | Metodología | es_PE |
dc.title | Aseguramiento de la calidad durante la ejecución del mejoramiento del emisor de Paiján bajo la metodología del PMBOK – 2021 | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingeniería | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0001-9168-8258 | es_PE |
renati.author.dni | 76649344 | |
renati.author.dni | 70188002 | |
renati.advisor.dni | 18112316 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Durand Orellana, Rocio del Pilar | |
renati.juror | Panduro Alvarado, Elka | |
renati.juror | Geldres Sánchez, Carmen | |
dc.publisher.country | PE | es_PE |