dc.contributor.advisorMerino Martinez, Marcelo Edmundo
dc.contributor.authorVelasquez Cruz, Carlos Manuel
dc.contributor.authorZavaleta Távara, Sergio Matías
dc.creatorVelasquez Cruz, Carlos Manuel
dc.date.accessioned2024-12-10T17:33:38Z
dc.date.available2024-12-10T17:33:38Z
dc.date.issued2024
dc.identifier.urihttps://hdl.handle.net/20.500.12759/52251
dc.description.abstractEl presente trabajo de investigación tiene como objetivo determinar la aplicación de la metodología last planner system en los procesos estructurales del edificio multifamiliar Mónaco ubicado en Monserrate, Trujillo. El estudio toma como punto de partida la puesta en práctica de la herramienta last planner system para el control, ejecución, seguimiento y administración de las actividades en los diversos procesos estructurales. De esta manera, busca verificarse a través de una mejor planificación y una mayor productividad. Como primer punto, se plantea y se desarrolla el plan maestro direccionado al armazón estructural y sus partidas respectivas, buscando que las actividades se organicen en un esquema general de inicio a fin. Asimismo, se desarrollan los LookAhead mensuales, teniendo en cuenta el cronograma del avance real y programado, detallando las actividades realizadas con sus plazos correspondientes. Continuando con el estudio, se realizan los planes semanales enfocados en periodos más cortos a lo largo del proyecto, generando un mayor detalle de las actividades a ejecutar. Por otra parte, se logra identificar las restricciones en cada proceso estructural, abordando estrategias de solución para mitigar estas limitaciones mediante un análisis y un formato de restricciones. Finalmente, se logra calcular el porcentaje del plan de cumplimiento (PPC) de las partidas estructurales semanalmente mediante la fórmula (%) provista, buscando así que se evidencie una mejoría en la planificación y ejecución de las actividades estructurales a través de la aplicación de esta herramienta lean constructiones_PE
dc.description.abstractThe purpose of this research work is to determine the application of the last planner system methodology in the structural processes of the Monaco multifamily building located in Monserrate, Trujillo. The study takes as a starting point the implementation of the last planner system tool for the control, execution, follow-up and administration of the activities in the different structural processes. In this way, it seeks to be verified through better planning and higher productivity. As a first point, the master plan is proposed and developed, directed to the structural framework and its respective items, seeking that the activities are organized in a general scheme from start to finish. Likewise, the monthly LookAheads are developed, taking into account the actual and programmed progress schedule, detailing the activities carried out with their corresponding deadlines. Continuing with the study, weekly plans are made focused on shorter periods throughout the project, generating a greater detail of the activities to be executed. On the other hand, it is possible to identify the restrictions in each structural process, addressing solution strategies to mitigate these limitations through an analysis and a format of restrictions. Finally, the percentage of the compliance plan (PPC) of the structural items is calculated weekly using the formula (%) provided, seeking to show an improvement in the planning and execution of the structural activities through the application of this lean construction tool.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada Antenor Orregoes_PE
dc.relation.ispartofseriesT_CIVIL_2659
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rights.urihttps://creativecommons.org/licenses/by/4.0/es_PE
dc.subjectLast Planner Systemes_PE
dc.subjectPlan Maestroes_PE
dc.titleAplicación del last planner system en los procesos estructurales del edificio multifamiliar Mónaco en Monserrate, Trujilloes_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada Antenor Orrego. Facultad de Ingenieriaes_PE
thesis.degree.nameIngeniero Civiles_PE
thesis.degree.disciplineIngenieria Civiles_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.00es_PE
renati.advisor.orcidhttps://orcid.org/0000-0003-4733-4959es_PE
renati.author.dni72741383
renati.author.dni72189303
renati.advisor.dni17983739
renati.typehttps://purl.org/pe-repo/renati/type#tesises_PE
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.discipline732016es_PE
renati.jurorHurtado Zamora, Oswaldo
renati.jurorGalvez Paredes, Jose Alcides
renati.jurorMedina Carbajal, Lucio Sigifredo
dc.publisher.countryPEes_PE


Files in this item

Thumbnail
Thumbnail
Thumbnail

This item appears in the following Collection(s)

Show simple item record

info:eu-repo/semantics/openAccess
Except where otherwise noted, this item's license is described as info:eu-repo/semantics/openAccess