dc.description.abstract | El presente trabajo de investigación tiene como objetivo proponer un plan de
gestión de riesgos en la construcción de un muro de contención en el interior de la
minera Boroo Misquichilca de tal manera que podamos identificar y evaluar los
posibles riesgos presente a lo largo del proyecto; de esta manera poder crear
planes o medidas de contingencia para evadir o mitigar dichos riesgos.
Se logro identificar 15 riesgos potenciales mediante el uso de formatos
proporcionado por la guía PMBOK 7ma Edición, dichos formatos nos sirvieron
también para poder analizar la probabilidad de incidencia del riesgo y su impacto
en la obra mediante una matriz en la cual asignamos un valor que nos permitió
analizar cuantitativamente el riesgo; de esta manera se logró asignar un nivel de
prioridad al riesgo entre moderado, alto y bajo. No obstante, fue de suma
importancia hacer uso del software RiskyProject Proffesional, ya que pudimos
obtener resultados de cientos de simulaciones que nos sirvieron para poder
visualizar la cantidad de riesgos afectan de manera crucial al presupuesto y a la
duración de proyecto, así mismo; se pudo reconocer las tareas que son cruciales
para el éxito del proyecto.
El software no solo predijo futuros sucesos en base a los riesgos que
identificamos con anterioridad, sino que también, nos arrojó la probabilidad de que
el costo final del proyecto aumente considerablemente.
Finalmente se crearon medidas de contingencia o planes de acción ante
posibles riesgos que pudieran ocurrir en el transcurso del proyecto, logrando
mantener el presupuesto y cronograma proyecto al inicio del proyecto, reduciendo
así pérdidas económicas considerables. | es_PE |
dc.description.abstract | The objective of this research work is to propose a risk management plan for the
construction of a containment wall inside the Boroo Misquichilca mine so that we
can identify and evaluate the possible risks present throughout the project; in this
way we can create contingency plans or measures to avoid or mitigate these risks.
We were able to identify 15 potential risks through the use of formats
provided by the PMBOK 7th Edition guide, these formats also helped us to
analyze the probability of risk incidence and its impact on the project through a
matrix in which we assigned a value that allowed us to quantitatively analyze the
risk; in this way we were able to assign a level of priority to the risk between
moderate, high and low. However, it was extremely important to make use of the
RiskyProject Professional software, since we were able to obtain results from
hundreds of simulations that helped us to visualize the number of risks that
crucially affect the budget and project duration, as well as to recognize the tasks
that are crucial to the success of the project.
The software not only predicted future events based on the risks we
identified earlier, but also gave us the probability that the final cost of the project
would increase considerably.
Finally, contingency measures or action plans were created for possible
risks that could occur during the course of the project, managing to maintain the
budget and project schedule at the beginning of the project, thus reducing
considerable economic losses. | es_PE |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada Antenor Orrego | es_PE |
dc.relation.ispartofseries | T_CIVIL_2536 | |
dc.rights | info:eu-repo/semantics/closedAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | es_PE |
dc.subject | Gestión | es_PE |
dc.subject | Riesgo | es_PE |
dc.title | Gestión de riesgos, PMBOK 7ma edición, en construcción de muro de contención en interior mina Boroo, Quiruvilca. La Libertad | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.grantor | Universidad Privada Antenor Orrego. Facultad de Ingenieria | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
thesis.degree.discipline | Ingenieria Civil | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.00 | es_PE |
renati.advisor.orcid | https://orcid.org/0000-0003-0836-0062 | es_PE |
renati.author.dni | 72912633 | |
renati.author.dni | 72621609 | |
renati.advisor.dni | 18173778 | |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.discipline | 732016 | es_PE |
renati.juror | Durand Orellana, Rocío del Pilar | |
renati.juror | Merino Martínez, Marcelo Edmundo | |
renati.juror | Medina Carbajal, Lucio Sigifredo | |
dc.publisher.country | PE | es_PE |